Settlement of all WBS time card costs to Resource cost center

$
0
0

Friends

 

 

How do I settle WBS secondary costs like timecards to the resource's cost center - The one who has entered time.

 

Suppose resource A enters time. His sender cost center is X.  it is passed to CO.

Resource B also enters time. His sender cost center is Y. it is also passed to CO.

 

When I settle the WBS:

 

Costs for resource A should be settled to cost center X and

Costs for resource B should be settled to cost center Y.

 

Is this possible using strategies and allocations?

 

Thanks in advance

 